Retainage in construction
In the United States, retainage is an amount of money withheld from progress payments to ensure that the construction work is completed. It acts as an incentive for the supply chain to fulfil all of their obligations under a contract, and provides a reserve of money to be drawn on if they do not complete and have to be replaced. The UK equivalent is known as ‘retention’.
Clients can retain money from main contractors who can in turn retain money from subcontractors who can retain from sub-subcontractors, and so on.
The amount of retainage varies according to the project and the region but it is calculated as a percentage of each interim payment. Typically 5-10%, the exact amount, and conditions for its release, can be negotiated between owners, contractors and subcontractors prior to signing contracts. Public projects often require retainage to adhere to state laws.
Whilst retainage is usually only a small portion of the payments made as the work is carried out, it can amount to a sizeable total value that can be a strong incentive to complete. However, it also creates cash flow problems for the supply chain, and can take a long time to release. As a result retainage has come under some criticism.
It is important that retainage is a fair amount, and that it is equitable, that is, that the amount withheld from subcontractors by the main contractor should not be greater than the amount withheld from the main contractor by the client. In addition, clients should release the retainage promptly once the work has been completed and accepted; and similarly, the main contractor must make prompt payment of the retainage to subcontractors.
In some contracts, the percentage of retainage will decrease as the work progresses to reflect the fact that the likelihood of failure to complete has also decreased. If payments are not made promptly, interest may be charged.
As an alternative to retainage, the contractor may deposit securities, and any interest accrued is then paid to the contractor.
[edit] Related articles on Designing Buildings Wiki
- Building codes.
- Construction supply chain payment charter.
- Contract sum.
- Final account.
- Holdback.
- Interim certificate.
- Mechanic’s lien.
- Miller Act.
- Practical completion.
- Retention.
- Retention held in trust fund.
- Right to payment.
- Stop work order.
- Subcontractor default insurance (SDI).
- Substantial completion.
- Surety.
- The problems with retention.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Changing expectations around competence and compliance
New information sheet from CIAT.
Grenfell investigation files passed to CPS
Angela Rayner apologises on behalf of the British state.
Electrical contractors need to understand the practical implications.
The real barrier to getting more value from digital technology.
Your guide to The Construction Reset at UKCW Birmingham.
Accommodating the Victorian and Edwardian working woman. Book review.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.